First phase of ESHS redevelopment completed ahead of schedule

Demolition and site clearance of old foundations at the Elmore Stoutt High School has been completed ahead of the January 7 deadline.

The project was undertaken by Sandwise Limited as they won the $136,079.50 contract to provide the demolition and clearance services.

The works began on December 10 and since then, workers have been working from 8 o’clock in the morning to four in the afternoon to complete the task during the allotted time frame.

While demolition was happening, BVI News noticed workers drilling through the old concrete foundation in the mornings and using an excavator to remove the heavy stones once the drilling stopped in the afternoon.

The debris was loaded into dump trucks and removed from the site.

Over the last few days, the workers levelled the area and poured asphalt on various sections.

READ MORE: BVI NEWS

U.S. VIRGIN ISLANDS WEATHER

SMUGGLERS USED KIDS’ LUNCH BOXES TO SHIP COCAINE FROM PUERTO RICO, PRO...

VI News Staff
4 years ago

Legislators Approve Zoning for 88-Unit Housing Development in St. John

VI News Staff
1 year ago

Cannabis Advisory Board Selects New Director Prior to Availability Con...

The Cannabis Advisory board spent most of Tuesday’s brief meeting in executive session, em...

VI News Staff
2 years ago

D’Amour Performs Well in Adverse Conditions in Shanghai at Stage II of...

VI News Staff
3 years ago

US Supreme Court Turns Away Casino Mogul Wynn's Bid to Challenge NY Ti...

VI News Staff
1 year ago