VI News Staff 4 years ago
VINStaff Verified #bvinews

First phase of ESHS redevelopment completed ahead of schedule

Demolition and site clearance of old foundations at the Elmore Stoutt High School has been completed ahead of the January 7 deadline.

The project was undertaken by Sandwise Limited as they won the $136,079.50 contract to provide the demolition and clearance services.

The works began on December 10 and since then, workers have been working from 8 o’clock in the morning to four in the afternoon to complete the task during the allotted time frame.

While demolition was happening, BVI News noticed workers drilling through the old concrete foundation in the mornings and using an excavator to remove the heavy stones once the drilling stopped in the afternoon.

The debris was loaded into dump trucks and removed from the site.

Over the last few days, the workers levelled the area and poured asphalt on various sections.

READ MORE: BVI NEWS

U.S. VIRGIN ISLANDS WEATHER

Public questions power of Human Rights Commission

VI News Staff
1 year ago

VIHFA to Pay $100 Million to Vitol on Friday Following HUD Approval of...

VI News Staff
2 years ago

VIWMA Updates St. Thomas Solid Waste Collection Schedule

The Virgin Islands Waste Management Authority (VIWMA) announces the updated weekly St. Tho...

VI News Staff
2 years ago

Hawley warns GOP Medicaid cuts are ‘morally wrong and politically suic...

VI News Staff
1 year ago

POLICE INVESTIGATING AFTER TEEN FOUND UNCONSCIOUS AT MARGARITAVILLE PO...

VI News Staff
4 years ago