First phase of ESHS redevelopment completed ahead of schedule

Demolition and site clearance of old foundations at the Elmore Stoutt High School has been completed ahead of the January 7 deadline.

The project was undertaken by Sandwise Limited as they won the $136,079.50 contract to provide the demolition and clearance services.

The works began on December 10 and since then, workers have been working from 8 o’clock in the morning to four in the afternoon to complete the task during the allotted time frame.

While demolition was happening, BVI News noticed workers drilling through the old concrete foundation in the mornings and using an excavator to remove the heavy stones once the drilling stopped in the afternoon.

The debris was loaded into dump trucks and removed from the site.

Over the last few days, the workers levelled the area and poured asphalt on various sections.

READ MORE: BVI NEWS

U.S. VIRGIN ISLANDS WEATHER

Bill in USVI calls for persons to be jailed or fined for lying to Gov'...

VI News Staff
4 years ago

Delegates to V.I. Constitutional Convention Hope Sixth Time’s a Charm

VI News Staff
1 year ago

Official says gangs killed dozens in small fishing village in Haiti’s...

VI News Staff
1 year ago

Career and Technical Education Stymied by Chronic Underfunding and Age...

VI News Staff
2 years ago

Liberty VI Continues to Expands Fiber Coverage Across USVI, Promising...

VI News Staff
1 year ago