First phase of ESHS redevelopment completed ahead of schedule

Demolition and site clearance of old foundations at the Elmore Stoutt High School has been completed ahead of the January 7 deadline.

The project was undertaken by Sandwise Limited as they won the $136,079.50 contract to provide the demolition and clearance services.

The works began on December 10 and since then, workers have been working from 8 o’clock in the morning to four in the afternoon to complete the task during the allotted time frame.

While demolition was happening, BVI News noticed workers drilling through the old concrete foundation in the mornings and using an excavator to remove the heavy stones once the drilling stopped in the afternoon.

The debris was loaded into dump trucks and removed from the site.

Over the last few days, the workers levelled the area and poured asphalt on various sections.

READ MORE: BVI NEWS

U.S. VIRGIN ISLANDS WEATHER

Tortured to death: Myanmar mass killings revealed

VI News Staff
4 years ago

Commissioner of Consumer Affairs Explains Reasons Behind Increasing Gr...

VI News Staff
4 years ago

$4.8M in Federal Funding Boosts Crime Prevention and Justice Programs...

VI News Staff
1 year ago

Roach Hopeful More Residents Will Take Vaccine With Pfizer Fully FDA A...

VI News Staff
4 years ago

Routine traffic stop yields arrest on illegal gun, ammunition charges

VI News Staff
1 year ago